|
Home > Awards> Carran Hill Water Treatment Works
Carran Hill Water
Treatment Works |
82.1% |
Project Team:
Client: Northern Ireland Water Service
Design and Construction:
Farrans (Construction) Ltd and Earth Tech Engineering (now AECOM)
|
Award presentation for
the Carran Hill project |
|
Project background
Carran Hill Water Treatment Works is situated on the
outskirts of Crossmaglen in County Armagh. The works
treats water from nearby Lough Ross, which historically
has been plagued with algae problems. The existing works
was reaching the end of its useful life and was struggling
to deal with the level of algae being produced during
the warmer summer months.
In November 2004, the joint venture partnership of
Farrans (Construction) Ltd and Earth Tech Engineering
was awarded a £10m contract to construct a modern
new treatment works that would produce high quality
drinking water in line with the latest EU directives.
Procurement approach
The main design and build contract was based on NEC
Option C (Target Cost Reimbursable) Conditions of Contract
and from the outset a partnering and integrated supply
chain approach was adopted as a means of achieving the
optimum value solution.
Being the fifth in a series of water treatment works
to be built as part of Water Service's Water Quality
and Treatment Framework, the contractors at Carran Hill
were able to adopt many of the lessons learnt from previous
contracts. At the core of the Framework is innovation
and best practice, with Water Service working with its
supply chain to implement 'lean thinking' modern construction
techniques to drive out waste in the design, construction
and commissioning of water treatment facilities. At
Carran Hill the latest construction and programme management
initiatives (including open book accounting and continuous
improvement) were adopted.
Key considerations
During construction work, the existing Carran Hill
WTW was to remain in operation and as part of the new
Carran Hill project, the old storage tanks were to be
refurbished and a new clear water tank constructed.
Only once the new works was fully commissioned was the
old works to be decommissioned and demolished.
Environment-conscious design
The new Carran Hill WTW has been carefully designed
so that its exterior blends in with the surrounding
countryside. Curved roofs and green cladding are two
of the aspects adopted to make the building more aesthetically
pleasing in a rural environment. In landscaping the
area, recommendations from the specially-prepared Ecology
Report were incorporated into the landscape plan. In
consultation with The Ulster Wildlife Trust, these included
the construction of an otter holt down at the works'
inlet pumping station.
The detailed landscape plan centred on the planting
of only native tree species, and during the contract
the plan was revised to minimise import and export of
material.
The project was designed to minimise the amount of
concrete used. Cast in situ concrete tanks, usually
used in the final stages of water treatment process,
were replaced by stainless steel tanks that were fabricated
off-site and set in place prior to the roof construction.
The footprint of the building was substantially reduced
and the finish levels reviewed to minimise the amount
of rock excavation
During construction, a percussion head was fitted to
the rock hammer to reduce the noise generated during
rock breaking.
Inside the works, the treatment process has been cleverly
set up to allow all the water entering the plant to
be recycled. This means that all water used during each
of the treatment stages, i.e. water used to wash out
filters, or water that is produced from the sludge process,
is put back to the source of the works
The works utilises a robust four-stage treatment process.
Extensive on line water quality instrumentation has
been incorporated into the design to monitor and control
the plant, allowing it to run automatically and with
minimum operator intervention. The plant status is available
via PC monitoring terminals located in the plant control
room, with group and common alarms available for transfer
to a telemetry station giving remote access and control
of the plant.
'Green' construction
Emphasis was also placed on utilising recycled building
materials. For example, the 300 tonnes of rebar used
in the concrete construction was manufactured from scrap
metal and the vast amount of plywood used in the shuttering
process was sourced from forests belonging to certification
schemes overseen by the PEFC Council (Programme for
the Endorsement of Forest Certification Scheme).
Waste management practices employed on site included
the segregation of all timber, rebar, and block/brick
prior to removal to a local recycling facility. During
construction all chemicals were stored in dedicated
bunded areas and a special settlement tank was provided
to contain any water pumped from excavations. To protect
the Lough, floating booms were placed along the waterway.
During Value Engineering workshops the team looked
closely at energy efficiency and reducing the amount
of power needed during operational hours. As a result,
heating is only provided in the administration section
of the building. The 'Power Correction Factor' target
for the plant has been set at 0.98 and the standby generator
can be used at peak times ('Peak Lopping') to generate
electricity for the plant.
Construction innovations
The forward-thinking aspect of 'Constraint Management'
was implemented right throughout the supply chain to
assist completion by the 'Target Completion Date'. To
achieve the best results, it was necessary to produce
a fully integrated programme incorporating the design,
procurement and construction phases and merging the
entire civil and M&E elements and key supplier programmes
into one schedule for monitoring and reporting purposes.
This initiative allowed the designers and suppliers
to plan their design and fabrication workload to suit
their resources and capabilities and maximised the potential
for off-site fabrication.
Key Performance Indicators & Respect for People
Initiatives
Adoption of 'Respect for People' initiatives and benchmarking
performance of key suppliers/ subcontractors on site
with respect to site safety, quality, workforce satisfaction,
working environment and team effectiveness, allowed
continuous feedback and improvement measures to be incorporated
during delivery of the project.
Community spirit:
Supply Chain Initiatives were established, allowing
a substantial proportion of the monetary value of the
project to be invested back into the community by sourcing
and using locally-based material suppliers and subcontractors.
A high level of community interaction was maintained
throughout the planning and construction stages and
in support of community initiatives, the Carran Hill
project team participated in a 10-mile sponsored walk,
which raised £2,532 for a local charity. In November
2005, the team was also delighted to welcome children
from the local primary school to the new works to give
them an insight into how the new plant would run.
|