|
home > awards
Thames Water
Ring Main Tunnel Extensions – AMP4 London
Resilience Programme: 4DCF Brixton To Honor
Oak |
75.8% |
Interim Client & Outline Design Award
Project Team: Thames Water Utilities Ltd (client) London
Clean Water Network (LCWN) and Mott MacDonald (design)
The Thames Water Ring Main (TWRM) was completed in
1994 and comprises a complete tunnelled ring around
the major water supply zones within the Greater London
area. Typically, the tunnel is located 40m below ground
and transfers up to 1100MLD of potable water.
The AMP4 London Resilience Programme includes the requirement
to construct two major tunnel extensions (4DCF and 6DCF)
to the Ring Main. The tunnels are required to transfer
up to 300MLD of potable water and will increase security
of supply for areas to the North East and South East
of London.
During the early stages of the project, a decision
was taken to register both projects for the CEEQUAL
award scheme to ensure the highest standards of environmental
good practice and design were achieved. The CEEQUAL
award is divided into two stages that represent the
key project milestones, namely;
- Stage 1: Interim
Award Stage for satisfactory completion of planning
and the outline design phase.
- Stage 2:
Whole Project Award Stage for satisfactory completion
of the construction phase.
The 4DCF Brixton to Honor Oak project has successfully
completed the Interim Award stage and the Award was
presented at a ceremony at the Institution of Civil
Engineering on 11 July 2007.
4DCF Brixton To Honor Oak
The southern tunnel extension from Brixton to Honor
Oak comprises a 2.5m internal diameter, driven 4.8km
from a new 55m deep shaft at Honor Oak Reservoir Site
to a new reception shaft at Brixton Water Treatment
Works. The tunnel will be constructed using pre-cast
concrete segments and an earth pressure balance tunnel
boring machine. Each site has its own engineering and
environmental planning challenges. The Honor Oak Site
is located on Metropolitan Open Land (MOL) and is used
as a nine-hole golf course. The site is bounded by residential
housing, a park, football club and a school. The Brixton
site is on operational land similarly bounded by residential
housing.
During the planning stages of the project, an Environmental
Impact Assessment Screening Opinion Report was prepared,
which stated that the project would not lead to any
significant environmental impacts and therefore the
main tunnelling works should proceed as Permitted Development.
Works undertaken during the planning and outline design
phase can significantly influence environmental impacts
during the construction phase. By highlighting key environmental
issues early and incorporating appropriate measures
into the outline design, a better overall environmental
performance will result.
Key actions undertaken by the Client-Design team during
the Interim Award stage included:
- Reducing construction impact
through careful consideration of locations for the
tunnel drive and reception shaft site. The outline
design removed the need to construct an intermediate
access shaft.
- An Environmental Management
Plan (EMP) was prepared, including an environmental
risk register, identifying key risks and mitigation
measures to be addressed by Thames Water and the contractor.
- A Tender Assessment Scoring
method was used which gave consideration to the contractor’s
environmental track record.
- Environmental screening surveys
were carried out to identify likely environmental
impacts (e.g. traffic, noise, groundwater, archaeology
and habitat surveys).
- A Project Communication Plan
for liaising with all key stakeholders was prepared.
The key stakeholders comprised local authorities,
residents and users of the golf club. Drop-in sessions
were held at the main shaft site and the local residents
were invited to hear about the project and raise any
concerns, which were fed back to the project team.
- A firm of architects were
appointed to design the site compound layout with
a view to reducing the amount of MOL taken up whilst
providing suitable access for operational requirements.
- A Landscape Plan was developed
in collaboration with London Borough of Southwark’s
Tree Officer to remove trees found to be in poor condition
and plant new trees at the Honor Oak Reservoir site.
- Pre-Construction Enabling
Works were designed and carried out to upgrade the
main access to the Honor Oak Site. Upgrades included
provision of a new pedestrian walkway and guardrail,
recycling centre and widening of the unmade road.
|
Before (top) and after
(bottom) |
|
Future Works – Construction Phase
Both 4DCF and 6DCF projects have been procured as Design
& Build contracts, using the Engineering Construction
Contract (ECC). The appointed tunnelling contractors
are required to develop the detailed design and carry
out the construction works. The construction works have
the potential to create the largest environmental impact.
Typically, the key environmental impacts identified
during the construction phase comprise:
- construction traffic nuisance
to local residents
- compliance with Environmental
legislations (Section 61 and EA approvals)
- detailed design of the tunnel-lining
system
- recycling and/or disposal
of tunnel arisings, primarily Thanet Sands, Chalk
and London Clay via other project sites or aggregate/gravel
pits.
- non-contamination of Source
Protection Zones (SPZ)
With the first part of the journey complete, London
Clean Water Network remain committed to working together
with the Design & Build Contractor to ensure the
high standards of environmental excellence are achieved.
|