|
home > awards
Norton-Fitzwarren
Dam |
79.8% |
Design Award
Designer: Hyder Consulting (UK) Ltd
The dam, designed by Hyder Consulting Ltd, is a flood
attenuation structure designed to prevent flooding in
the village of Norton Fitzwarren near Taunton. With
potential flooding under control, residential development
will now be permitted on the redundant cider factory
site in the centre of the village.
Client for the project is the Norton Fitzwarren Consortium,
comprising developers Barratt, Bellway and Strongvox.
Contractor is Jackson Civil Engineering Ltd and it is
planned to seek a combined Design & Construction
award on completion of construction.
The project comprises the construction of a 450-metre-long
earth dam across the valley of the Halse Water. It is
5.25m high at its highest point and when full will impound
750,000 cubic metres, meaning it falls within the remit
of the Reservoirs Act 1973. It has a clay core and sheet-pile
cut-off, with all the bulk earthworks materials being
won from site. The excavation resulting from this is
being retained and turned into a valuable wetland feature.
A 2.5-wide by 2.0-metre-high culvert will allow normal
flows to pass through the dam uninterrupted but will
limit the amount of water that flows downstream during
abnormally high flows and thus reduce flood risk. The
dam will start to impound when flows exceed the capacity
of the culvert but it is only expected to fill to the
top when a flood event with a return period of one in
a hundred years is experienced (with an allowance of
an extra 20% for climate change).
The site is in a rural agricultural setting close to
a small hamlet. The ecology of the site is varied, with
a number of protected species, including great crested
newts, reptiles, bats, otters and badgers being present.
Advance works were carried out to minimise impacts on
local wildlife and provide new habitats to compensate
for the dam construction where these were required.
Post-construction habitat creation works will result
in the ecological value of the dam and surrounding area
being higher than the pre-construction situation.
Extensive areas of woodland and hedge planting will
be undertaken to mitigate disturbance to the existing
vegetation/field pattern and for visual amenity. It
has been designed to have immediate visual impact to
soften and eventually screen views from Monty's Farm
hamlet. Planting will be undertaken using locally grown
native species where possible.
In gaining its award, key features of the project have
included:
- Winning all the bulk earthworks
from within the site so as to minimise impact on local
roads. and communities and CO2 emissions in transportation.
- Creating a permanent wetland
in the resulting excavation
- Advanced Works Contract to
remove hedgerows and temporarily exclude newts from
the site.
- Creation of other ecological
mitigation measures including a new pond and otter
ledges.
- Landscaping to screen the
hamlet from the dam.
|