|
home > awards
Dartford Creek |
84.6% |
Whole Project Award
Project Team: Environment
Agency (client), Ove
Arup & Partners (designer), Team
Van Oord (contractor)
The Project
Dartford Creek is one of the last remaining natural
tidal creeks in London. The flood embankments along
Dartford Creek provide 1:1000 year flood protection
to 620 residential and commercial properties. Over time,
the stability of these embankments had been undermined
by natural migration of the river channel, where erosion
and over-steepening of the banks caused geotechnical
slip failures. The flood embankments had suffered multiple
failures in recent years, urgently requiring a permanent
solution.
The £5m Grant-in-Aid scheme, designed by Arup
and constructed by Team Van Oord for the Environment
Agency, returned the channel to its historical position
and provides long-term erosion protection to the flood
embankments. The integrated team approach ensured completion
ahead of programme and within the target cost.
Use of Brushwood Faggots
The Environment Agency required a soft-engineered solution
using sustainable techniques to restore flood defence
robustness, integrity and create salt marsh habitat.
Although brushwood faggots have been used for centuries
in riverbank reinforcement, this modern use is innovative
both in terms of scale and interaction with the natural
processes of scour and siltation.
Design
The design solution was to re-profile the alluvial
slopes to establish a flatter, stable slope, protecting
the slope toe from erosion and combating deep-seated
rotational slip failures in the flood embankments.
The sustainably sourced brushwood faggots, held in
place by timber stakes, formed a matrix which reduced
water velocity and encouraged silt accumulation on the
foreshore. The brushwood was carefully profiled to create
a naturalistic river meander. Rock rolls (circular gabion
baskets) were used to protect the brushwood toe. This
protection from undermining and erosion was critical
to the design.
Steel sheet piles were placed along the toe of the
flood embankments to provide a secondary defence line
and to resist deep geotechnical slip failures. This
technique was verified through the application of thorough
geotechnical design principles, producing a sustainable
engineering solution and enhancing the local ecology
while protecting the Biological Action Plan (BAP) habitat.
Monitoring Programme
One of the Environment Agency’s main concerns
was whether steepening the opposite foreshore would
lead to large scale slips and loss of salt marsh. A
five year monitoring regime implemented during construction
allows early intervention should any adverse impacts
from the remedial works become apparent.
LIDAR surveys of this inaccessible area coincident
with vegetation surveys provided detailed monitoring
of changes in foreshore level and ecological condition
and function. Findings show that the creek responded
broadly as predicted. There is no evidence of adverse
impacts on the opposite salt marsh or flood embankments.
|