|
home > awards
A590 High and
Low Newton Bypass |
85.4% |
Whole Project Award
Project Team: Highways
Agency (Client), Jacobs
(Client Representative), Pell
Frischmann (Contractor’s Designer), Laing
O’Rourke (Contractor), Golder
Associates (Designer’s Environmental Sub-consultants)
The Project
|
Award presentation
for A590 High and Low Newton Bypass |
|
The A590 trunk road provides the strategic link between
south and west Cumbria and the national motorway and
trunk road network. The new bypass is located up to
300 m west of the existing A590 at High and Low Newton
and Ayside villages and lies wholly within the Lake
District National Park. It provides direct access to
the Furness Peninsula, the western coastal strip, and
the southern Lake District attractions.
The A590 High and Low Newton Bypass is 3.8 km in length
and links the Lindale bypass to the Barrow Banks Diversion,
effectively removing through-traffic from the existing
road in High Newton and Low Newton by providing a new
high-standard route for quick and safe travel for road
users. In addition, this improves accessibility for
the existing communities and areas of industrial, commercial
and tourist development.
Construction of the bypass comprised the following
works:
- 3.8 km of dual two-lane carriageway
- five structures for crossing the bypass
- two grade-separated junctions at the northern and
southern tie-ins
- false-cutting and earth-mounding to mitigate the
visual intrusion
- wildlife mitigation measures
Environmental Management
An Early Contractor Involvement (ECI) contract ensured
that all the challenges faced by the Project Team were
identified early, allowing mitigation measures to be
taken. The main challenges the Team faced were:
- the introduction of a new dual carriageway in a
rural location designated as a National Park
- high populations of protected species
- designing and constructing a scheme to current standards
and expectations while honouring the commitments made
at the Public Inquiry 15 years ago.
Landscape
The A590 runs through an attractive rural landscape
in the southern part of the Lake District National Park.
The undulating land resulted in extensive cut and fill,
with embankments and cuttings in excess of 10 m. The
visual impact of the new road were a major concern to
local residents and extensive mounding, up to 4 m high
in some areas and including approximately 250 m of false
cutting and mounding, was constructed to help screen
the bypass from adjacent properties.
To help reduce the visual impact of the scheme, 3.85
ha of land was acquired temporarily to help re-grade
and shape embankments to a much gentler incline, allowing
for integration within the natural landscape. Approximately
8.4 km of new dry-stone walling were constructed at
1.4 m in height and designed to match the existing vernacular.
Trial wall panels were prepared to ensure they were
to the satisfaction of the Lake District National Park
Authority. Existing walling material was re-used and
additional stone material sourced locally.
Structures, including the underpass wing walls and
culvert head walls, were also faced with locally sourced
stone and existing stone gate posts were retained and
incorporated into new field accesses.
Edge-of-carriageway drainage channels were replaced
with filter drains, profiled to a channel shape and
using local stone, thereby combining the benefits of
a traditional filter drain with an edge-of-carriageway
channel and avoiding the inappropriate visual effect
of concrete channels. A major planting programme was
developed, including 6.8 ha of native woodland and woodland
edge and 380 linear metres of new hedgerow to screen
the bypass and aid with landscape integration. In addition,
5.3 ha of wildflower seeding using local plant species
was incorporated into the scheme. Off-site planting
at the northern end of the scheme was implemented to
screen properties, and two mature ash trees were successfully
translocated at Barrows Green.
Ecology & Biodiversity
Demolition of Black Beck Hall and its associated outbuildings
was required to allow for the construction of the bypass.
A small number of bat species, mainly the Common Pipistrelle,
used Black Beck Hall as a roost site, roosting within
crevices behind hanging slates, facia boards and within
stonework.
Prior to the demolition of Black Beck Hall an alternative
roost site was created by renovating and converting
a pair of semi-derelict pig sties, which were immediately
adjacent to the existing roost site and well-connected
to the wider countryside. This included replacing roof
timbers, providing horizontal timber battens, infilling
windows, providing spaces within newly laid ridge tiles
to allow bats to access the interior of the building,
providing bat boxes and creating a panel of hanging
slates to the exterior of the building. Works were programmed
to allow for the time constraints associated with bats.
Bats were excluded from Black Beck Hall by carefully
hand-dismantling the building under supervision from
an ecologist, any bats taken by hand were moved to the
alternative roost and released at nightfall.
As part of the permanent design, an overhead bat guidance
structure was constructed to direct bats across the
bypass. Cavities were incorporated into the walls of
underpasses, to be used as roosting places for bats.
To minimise maintenance these are self-cleaning.
Approximately 8.6 km of badger fencing was erected
to stop badgers from crossing the bypass, and a customised
cattle grid was installed on the cycle path to prevent
badgers accessing the carriageways via the cycleway.
Four badger tunnels and one mammal tunnel were provided
along the scheme and purpose-made badger gates were
built into the new dry-stone walls to allow badgers
to access the tunnels.
Deer reflectors mounted on 1200-mm-high posts were
provided alongside the carriageway at the northern end
of the scheme to deter deer from crossing the bypass.
Four balancing ponds were constructed to regulate surface
water run-off, each with a petrol interceptor, and were
planted with marginal planting to increase ecological
biodiversity.
Community
A public exhibition was held for the start of works,
in High Newton Village Hall on 25 and 26 July 2006.
This was followed by a turf-cutting ceremony. Wielding
the spades were the oldest and youngest members of the
community.
Tree planting started in November 2007, when children
from Levens Valley Primary School joined the Project
Manager to plant a young ash tree, the first tree to
be planted along the bypass. This event was an opportunity
for local children to get involved and coincided with
National Tree Planting week.
On 7 February 2008, children from Cartmel Church of
England Primary School joined Graham Dakin, the Highways
Agency’s Project Manager, at an event to bury
a time capsule near the new road. The youngsters all
decided what items went into the capsule.
Two public rights of way were affected by the scheme
and were stopped up with new footpaths provided upon
completion. The Project Team worked in conjunction with
the Public Rights of Way Officers from the Lake District
National Park in an endeavour to provide alternative
routes during the construction period. Unfortunately,
due to adverse weather conditions and a number of other
constraints, this was not possible for the entire duration
of works
Materials & Waste
To minimise waste, all existing material was re-used
where possible: old road planings, old walling stones,
gate posts, topsoil and subsoil. Material was sourced
locally where possible and a large proportion of material
came from a secondary aggregate source. Earthworks balanced
with only a minimal import of 12,000 cubic metres, which
was brought in under waste management exemptions from
local demolition sites.
Slate, as a local material, was used for wall capping
and structural backfill. Its high permeability also
rendered it suitable for use in conjunction with multi-cellular
back-of-wall drainage on the structures, instead of
traditional blockwork.
Upon decommissioning of the site compound, and to reduce
waste to landfill, materials were re-used by local farmers
under waste management exemptions.
|