|
home > awards
Axbridge Raw Water
Treatment Works |
91.2% |
Whole Project Award
Project Team:
Bristol Water Plc (client), Black
& Veatch (designer), Costain
(contractor)
The Project
Aim of the project was to provide a replacement plant
for the treatment of raw river water pumped from the
River Axe and discharged into the Cheddar Reservoir.
The site was equipped with large settlement tanks for
a temporary treatment plant, erected some years before
for drought relief. In addition, over a kilometer of
unsightly overland pipeline, laid along the footpath
rim of the Cheddar reservoir, had to be moved and buried
at the embankment base.
The objective was to remove all of the temporary plant
and pipeline, and to build a new state-of-the-art treatment
works to remove silt, chemicals and organic matter from
the river water for discharge into the reservoir. The
reservoir itself is normally spring-fed from the Mendip
Hills and it was feared that the River Axe water, if
not treated to a high standard, could introduce nitrates
and other chemicals to the water, causing algae blooms
and excessive weed growth.
Recycling the old site
In early 2007, the existing tanks and pipe work were
dismantled and stored for re-use at another site. The
existing concrete base was re-used with little modification
for the new treatment plant and actiflow units. The
new plant was designed to fit onto the old concrete
base, thus reducing the amount of demolition and materials
required.
Building the Treatment Works
Formwork for the bases of the four actiflow units was
added and erection of the off-site prefabricated structure
began in May 2007. By June, the framework was taking
shape. The dark green cladding of the building was specifically
chosen to blend with its surroundings – a critical
aspect for this site on the fringes of the Mendip Hills
AONB. Extensive woodland planting was undertaken to
provide additional screening for the new plant, as well
as increasing the habitat for Biodiversity Action Plan
Species – including bats.
By August, construction of the building was complete
and the task of connecting the plant could begin. The
entire water treatment plant was completed in October
2007, several months ahead of schedule. A rigorous testing
programme and training of the plant’s operational
staff followed.
Innovative approaches taken
A number of innovative technologies were used to improve
sustainability performance of the site. These included:
- For durability and low lifetime
maintenance, stainless-steel pipe work was used in
preference to coated materials.
- Grasscrete roads were laid
in preference to tarmac, thereby saving costs on additional
drainage and omitting the need to obtain Environment
Agency discharge consents.
Community consultation
The repositioning of the pipeline along the rim path
of the reservoir presented its own challenges, as the
pathway around the reservoir has a high amenity value
and is used by hundreds of walkers, bird watchers and
anglers every week. For safety reasons, it had to be
closed to the public for several weeks whilst the work
was being completed.
Extensive consultation was undertaken with the local
Axbridge Town Council and Cheddar Parish Council, and
public exhibitions were held in both towns. Letter drops
were made to local residents and the local angling club
consulted. Large advance warning notices were erected
at all entrances onto the rim path.
As a result of these efforts, not a single complaint
was received from members of the public during the closure.
|
Team members at the
Axbridge exhibition |
|
Relocating the pipeline
The removal of the overland pipe was a real feat of
skill by the engineers. Originally it was proposed that
the 1km pipe would be cut into small sections, lowered
down the steep embankment and then re-jointed.
However, a method was devised using two large excavators,
one at the top, with a sling attachment to lift it from
the path and over the rim, and one at the base of the
embankment, equipped with large forks to catch and reposition
the pipe. This approach resulted in considerable savings
in terms of manpower and costs for re-jointing the pipe.
An additional pipeline was constructed alongside the
repositioned pipe, thus providing a dual system to transport
the raw water from the River Axe for treatment and taking
the treated water from the new treatment plant to the
discharge point into the Cheddar Reservoir.
The opportunity was also taken to renew and refurbish
the toe drainage system along the base of the reservoir
embankment. The system had become damaged and blocked
over the years, and now much of the adjacent pastureland
had standing water or marshy conditions. The refurbishment
has led to a real improvement to the area for grazing
stock.
Looking after the environment and the community
The environment in which this project was undertaken
had special significance for the way the contract was
handled. The Cheddar Reservoir is a nationally important
water for the over wintering of thousands of waterfowl.
Large numbers of birds arrive in the autumn from the
Somerset Level Wetlands and depart at the beginning
of spring to breed on the hundreds of minor waterways
that criss-cross the area.
Protection to these flocks is afforded by winter SSSI
status for the reservoir. All of the work to remove
the overland pipeline was scheduled for the period outside
of the winter season. A small river traversing the site,
the Ellenge Brook, was given special fencing protection
within the compound area.
Along the route of the pipeline, leakage from the toe
drainage had led to the development of marshland, and
a large reed and sedge bed had grown on an area of around
two acres, in what should have been good quality grazing
land. There was a possibility that this wet area would
cause damage to the reservoir embankment in future years.
Refurbishment of the toe drains cured the leakage problems.
However, due to the SSSI restrictions on the reservoir,
this work had to be done during the bird-breeding season
and a winter inspection of the area had shown that,
in previous seasons, some of the wildfowl had started
to use the area to breed. The area was therefore hand-cut
to ground level in late February, before the birds had
moved off the reservoir, in order to dissuade them from
nest-building on this site. The new drainage has now
replaced a muddy swamp with lush pasture and a substantial
increase of butterfly and other invertebrate insect
life has been observed.
Working with the community
During construction, members of the town council were
invited for an evening visit to the site, and the contractor
and project client made a joint donation to the town’s
Civic Trust to bedeck the town with hundreds of flowering
plants and hanging baskets for their Britain-in-Bloom
entry. Costain also provided a new surface to The Cheddar
Angling Club’s car park near the reservoir, as
a gesture of thanks for allowing part-use of the car
park for material storage during the construction works.
Jim Ludkins of the Axbridge Town Trust receives a cheque
from Andy Smith, Costain’s Liaison Manager and
Paul Kelson from Bristol Water Corporate Affairs office.
|