|
Home > Awards > Moneymore Flood Protection Scheme
Moneymore Flood
Protection Scheme |

93 %
|
Construction-Only Award
Project Team:
Client: DARD
Rivers Agency
Design: DARD
Rivers Agency & DAWSON-WAM
Ltd
Construction: DAWSON-WAM
Ltd
The project
Moneymore is a small village located on the outskirts
of Magherafelt in County Londonderry, Northern Ireland.
Within the village there are two housing developments
which are bordered by the Coltrim and Ballymully Rivers.
Through recent years the Ballymully River has over-topped
its banks on several occasions during periods of prolonged
and heavy rainfall. This combined with upstream run-off
from Slieve Gallion, poses the potential risk of serious
flooding to some 100 dwellings.
In February of 2008, DAWSON WAM Ltd were appointed
as the main contractor by the Department of Agriculture
and Rural Development Rivers Agency (DARDNI) to construct
new flood defences and reduce the risk of flooding to
a 1 in 100 year event. The works were to include:
- The supply and installation
of 510 lin/m of steel-sheet piled floodwall
- 230 lin/m of contractor-designed
flood barrier
- Installation of back
drainage
- Supply and placement of 1500
tonnes of rock armour for toe protection
- Installation of various fishery
measures, including areas of spawning gravel, ‘D’-shaped
groynes, plunge pools, etc
- Reinstatement of 40 riparian
gardens
There were several environmental
and construction-related challenges to overcome that
required strategic design, programming and implementation:
- All tree felling and riverbank
clearance had to be carried out between the 1st September
and the 29th February to avoid the bird nesting season
- No work was permitted within
the river corridor between 1st November and 14th April
to avoid the spawning season
- Routine water course sampling
had to be conducted throughout the course of construction
to monitor silt/sediment
- Piled flood defences had
to be installed as close as 300mm to existing dwellings
- Piles had to be toed into
sandstone to depths of up to 5m
- Vibration & noise monitoring
had to be carried out during all piling operations
- All work had to be carried
out within a 3–5m wide wayleave along the top
of each riverbank
Innovative alternative
design proposal
Due to the construction restrictions on this project,
DAWSON-WAM Ltd submitted an alternative design proposal
to construct a secant piled floodwall with a cast-in-situ
concrete top wall in lieu of steel sheet piles. Through
an integrated team approach
and early contractor involvement the alternative design
proposal was accepted by the client as it was deemed
to have the following advantages:
- Using a pile press/crush system
it was doubtful that the mandatory pile depths into
the underlying sandstone specified by the client could
be achieved. Utilising DAWSON-WAM’s secant piling
system guaranteed that the piles could be cored to
the required depth.
- The secant piling operation
could be carried out using a silent & vibrationless
rig which could install piles as close as 50mm from
dwellings without causing any damage.
- There was no procurement
time for materials allowing the contract to be implemented
within the restricted working times during the same
calendar year.
- DAWSON-WAM proposed the use
of a ‘stone look’ formliner to construct
the cast-in-situ top wall. All riparian’s were
approached on an individual basis to canvas opinion,
and it was widely preferred for its aesthetics as
opposed to the painted sheet-piled wall.
- There were substantial energy
savings through both material choice and construction
methods adopted.
Raising the bar
Prior to commencement, the construction
team produced a range of detailed and extensive plans
in order to establish a high benchmark from the outset.
These plans included, but were not limited, to:
- Green Travel
- Energy Management
- Air Quality
- Sediment & Erosion Control
- Pollution Contingency
- Site Waste Management
- Customer Care
Through working collaboratively
with CEEQUAL and the client, the bar was further raised
throughout the project with all team members committed
to going the extra mile. Examples of such measures were:
- Electrofishing of the watercourse
to remove small fry and restock in the local hatchery
further downstream prior to commencement of the works
- Recycling of spawning gravel
from upstream gravel traps for the construction of
the new fishery measures
- All 1500 tonnes of rock armour
used for toe protection was recycled material
- All felled trees were logged
and stacked along the riverbanks on completion to
create habitats for invertebrates
- All plant & equipment
used bio-degradable oils in case of accidental spillages
- 98% of inert and non-hazardous
waste material was sent for recovery in a waste to
energy plant
- All labour, sub-contractors
and material suppliers were sourced within an 18 mile
radius to minimise the carbon footprint of the site
- Extensive silt control mechanisms
were installed within the river to prevent migration
of silt downstream while installing the toe protection
and fishery measures
Customer care & community liaison
DAWSON WAM’s contracts manager was appointed
as the contractor’s public liaison officer. Prior
to commencement each riparian was individually visited
outside working hours to discuss the scheme and ease
any concerns. Through dealing promptly and effectively
with the smaller concerns, residents developed the confidence
and trust that bigger problems would be addressed in
a similar manner. Regular visits, letter drops, public
meetings and a 24hr emergency contact number all aided
in making this a ‘pain-free’ project. During
unprecedented flooding one Saturday evening, contracting
staff were onsite during the event. Staff remained late
into the evening until the peak of the flood had passed,
providing assurance to residents by monitoring the works
and aiding with sandbagging.
On completion of the project no complaints had been
received in what was deemed to be an extremely high-public-profile
scheme. Instead, several letters of commendation were
received from residents, the Police Service of Northern
Ireland (PSNI), Road Service and a number of charitable
and community organisations, praising the way the scheme
was implemented. This was reinforced further through
the presentation of a ‘Silver’ Considerate
Constructor’s Award.
|